Nevada Construction Law FAQ
Nevada construction law is statutory law. Lien deadlines, defect notices, retention limits and licensing rules are set by the Nevada Revised Statutes, and the answer to most construction questions in this state turns on a specific section of them. The answers below were written by Leon F. Mead II, author of Nevada Construction Law, and each one names the statute it rests on and the section of the treatise that covers it in full.
Mead Law Group has served Nevada’s construction industry for 30 years. The questions here are the ones Nevada owners, contractors, subcontractors and suppliers actually ask.
Disputes and legal action against a contractor
Is it worth suing a contractor?
Often yes, because Nevada changes the economics before any lawsuit: a homeowner can complain to the State Contractors Board under NRS Chapter 624 and claim up to $40,000 from its Recovery Fund (NRS 624.510), and a prevailing lien claimant recovers attorney’s fees (NRS 108.237). The real question is the contractor’s license, bond and collectability.
Nevada Construction Law (2027 ed.), Ch. 2, §2:11; Ch. 8, §8:22.
How do you take legal action against a contractor?
Put the complaint to the contractor in writing, then file with the Nevada State Contractors Board under NRS Chapter 624, which can discipline the license and opens the Recovery Fund to homeowners. For a residential defect, NRS 40.645 requires a certified-mail notice and a chance to inspect and repair before suit. For other suits, consult your attorney.
Nevada Construction Law (2027 ed.), Ch. 2, §2:17; Ch. 7, §7:5.
Can I sue a contractor for not finishing a job?
Yes. Abandoning a job is a breach of contract, and the owner recovers the reasonable cost to complete above the original contract price. If the contractor was unlicensed, NRS 624.700(4) voids the contract from the start, and a homeowner may also claim against the Contractors Board Recovery Fund (NRS 624.400 et seq.).
Nevada Construction Law (2027 ed.), Ch. 5, §5:12; Ch. 2, §§2:4, 2:11.
Related: Contract drafting, review, negotiation and dispute resolution · Mediation and arbitration
Mechanics liens
How long do you have to file a mechanic’s lien in Nevada?
A Nevada notice of lien must be recorded within 90 days after actual completion of the work of improvement or the claimant’s last work, whichever is later, or within 40 days after a valid notice of completion is recorded (NRS 108.226). On residential projects a 15-day notice of intent to lien comes first.
Nevada Construction Law (2027 ed.), Ch. 8, §§8:8, 8:14.
What are the lien rights in Nevada?
Anyone who furnishes labor, materials, equipment or services to improve private property in Nevada holds a statutory lien on that property for the unpaid price of the work (NRS 108.221–108.246). Subcontractors and suppliers must first serve a Notice of Right to Lien under NRS 108.245, and the work must be licensed (NRS 108.222).
Nevada Construction Law (2027 ed.), Ch. 8, §§8:1–8:9.
Can I file a mechanics lien without a lawyer?
Yes; NRS Chapter 108 does not require an attorney, and NRS 108.226 supplies the form. The risk is in the details: the lien must be verified, timely, recorded in the right county and preceded by the required notices, and timely served. A frivolous or excessive lien can be expunged with fees awarded against you (NRS 108.2275).
Nevada Construction Law (2027 ed.), Ch. 8, §§8:9, 8:16, 8:26.
Is there a statute of limitations on mechanics liens?
Yes. A recorded Nevada lien binds the property for only six months unless a foreclosure action is filed or a written extension is signed, notarized and recorded within that period, and no extension can carry the lien past one year from recording (NRS 108.233). After that it has expired for all purposes.
Nevada Construction Law (2027 ed.), Ch. 8, §§8:21–8:22.
How do you get a lien removed without paying?
Move under NRS 108.2275 to expunge a frivolous lien or reduce an excessive one: the court sets a hearing on 15 to 30 days’ notice, decides on affidavits and evidence, and awards fees to the prevailing party on a frivolous-lien challenge. Liens recorded late or without the NRS 108.245 notice are removed this way. This is not simple. You should consult counsel before attempting.
Nevada Construction Law (2027 ed.), Ch. 8, §8:26.
How do you bond off a mechanics lien?
Record a lien release bond under NRS 108.2413–108.2425 for 1.5 times the lien amount, issued by a Nevada-licensed surety on the U.S. Treasury list, and serve a copy on the lien claimant. Recording releases the property; the claim attaches to the bond, and the claimant has nine months after service to sue on it.
Nevada Construction Law (2027 ed.), Ch. 8, §8:25.
Do lien waivers need to be notarized in Nevada?
No. Nevada lien waivers must follow the four statutory forms in NRS 108.2457(5), which call for a signature and date, not a notary. What matters more is NRS 108.2457(2): no waiver is effective until the claimant is actually paid, and a bounced check voids even an unconditional release.
Nevada Construction Law (2027 ed.), Ch. 8, §8:28.
Related: Mechanics lien and payment disputes
Construction defects
What constitutes a construction defect?
Under NRS 40.615 a constructional defect is a defect in the design, construction, manufacture, repair or landscaping of a new residence, an alteration or addition, or an appurtenance that presents an unreasonable risk of injury, or was not done in a good and workmanlike manner and proximately causes actual physical damage. A code violation alone no longer qualifies.
Nevada Construction Law (2027 ed.), Ch. 7, §7:3.
What is the statute of repose for construction defects in Nevada?
Ten years from substantial completion. NRS 11.202 bars any action for a deficiency in the design or construction of an improvement more than ten years after the later of final inspection, notice of completion or certificate of occupancy, with an exception for fraud; a Chapter 40 notice tolls the period up to one year (NRS 40.695).
Nevada Construction Law (2027 ed.), Ch. 7, §7:7.
How long is a contractor liable for latent defects?
In Nevada a contractor’s exposure for a latent defect ends ten years after substantial completion under NRS 11.202, whenever the defect is discovered; the separate latent and patent periods were consolidated in 2015 and set at ten years in 2019. Fraud removes the bar, and a timely NRS 40.645 notice tolls the clock.
Nevada Construction Law (2027 ed.), Ch. 7, §7:7.
Getting paid: change orders, retention and bonds
Who pays for change orders in construction?
The owner pays for owner-directed changes at the price fixed in a written change order. Under Nevada’s Prompt Payment Act, an owner or general contractor who receives a written change order request and neither issues nor rejects it in writing within 30 days is deemed to have accepted it, price and time (NRS 624.610, 624.626).
Nevada Construction Law (2027 ed.), Ch. 3, §3:20; Ch. 4, §4:11.
Are pay-when-paid clauses legal in Nevada?
Not as most subcontracts write them. In APCO Construction v. Zitting Bros. Construction, 136 Nev. 569 (2020), the Nevada Supreme Court held pay-if-paid clauses unenforceable where they waive or limit a subcontractor’s Prompt Payment Act rights (NRS 624.624–624.630), and the Act lets an unpaid subcontractor stop work despite such a clause (NRS 624.626). This is a disputed area of law however.
Nevada Construction Law (2027 ed.), Ch. 3, §§3:19, 3:22.
What does 10% retainage mean?
Retainage is the share of each progress payment held back until the work is complete. Ten percent is common elsewhere, but Nevada caps it at 5 percent: on private work retention may be withheld only if the written contract allows it and never above 5 percent of the payment (NRS 624.609, 624.624); public works follow NRS 338.515.
Nevada Construction Law (2027 ed.), Ch. 3, §3:6; Ch. 6, §6:27.
How do you make a claim on a payment bond?
On a Nevada public work over $100,000 the general contractor must post a payment bond (NRS 339.025), which replaces lien rights because public land cannot be liened. A claimant without a direct contract with the general contractor serves a 30-day preliminary notice, a claim notice within 90 days after last furnishing, then sues within one year (NRS 339.035, 339.055).
Nevada Construction Law (2027 ed.), Ch. 6, §6:25.
Related: Public contracting · Mechanics lien and payment disputes
Licensing and delay
What are the laws and requirements for contractors in Nevada?
Anyone who bids or contracts to build, alter or repair in Nevada needs an active State Contractors Board license under NRS Chapter 624, in the right classification and monetary limit. Bidding or working without one is unlawful and the contract is void (NRS 624.700), with fines of $1,000 to $50,000; the handyman exemption covers only sub-$1,000, permit-free repairs (NRS 624.031).
Nevada Construction Law (2027 ed.), Ch. 2, §§2:1–2:4.
How much work can you do without a contractor license in Nevada?
Very little. NRS 624.031(6) exempts only repair or maintenance work worth less than $1,000, labor and materials combined, that needs no building permit and involves no plumbing, electrical, HVAC or life-safety trade. Splitting a larger job into sub-$1,000 pieces to avoid licensing is itself a violation (NRS 624.3014).
Nevada Construction Law (2027 ed.), Ch. 2, §§2:3–2:4.
What are my rights if construction is delayed?
Your contract controls first: it fixes the completion date, defines excusable delay and sets the notice steps for time extensions and delay costs. A clause forcing a contractor to waive delay damages is void under NRS 108.2453(2)(e) where the delay was unreasonable, not contemplated at contracting, or not the contractor’s fault.
Nevada Construction Law (2027 ed.), Ch. 4, §4:12; Ch. 5, §5:9.
Related: Administrative law, licensing and regulatory compliance · Construction law
This page is general information about Nevada law, not legal advice, and reading it does not create an attorney-client relationship. Statutes and case law change, and the result in any matter depends on its own facts. Consult a Nevada attorney about your situation before acting.